| Project description: |
 |
 |
Maintain traffic lanes open at all times during rush hours (night closures) |
 |
Repairs of concrete structures and bridge |
 |
Concreting on tunnel ceiling |
 |
Replacement of lighting, traffic light structures |
 |
Anti-blinding fences and setting up impact attenuators |
 |
Other related work on Decarie Highway (Highway 15), and service roads on North and South sides of Decarie tunnel and Turcot interchanges. |
| Challenge: |
 |
 |
Coordination of work phases and maintaining traffic lane reopenings on time every morning |
 |
Sound control (urban and night construction project) |
 |
Tunnel was sealed off at both ends during each shift. |
| Value of contract: 20 M $. |
 |
|
|
 |
 |
 |
 |
 |
|